ULSTER UNIVERSITY
This large scale project involving 3 phases was completed over a three month period in 2015. The move itself consisted of:
- Transport and installation of 100’s of University equipment and machinery.
- Installation of natural gas, compressed air and oxygen supplies to machinery.
- Disconnection & Reconnection of approx 60 no. 3 phase electrical supplies to machinery.
- Large machinery had to be relocated by crane.
- 2000 lm of library book stock packed and moved in sequence to new library.
- Dismantling, transfer & installation of all library shelving into the new library.
- Acrow props installed to provide additional building structure support.
- Approx 120 no staff were relocated with 800 crates been used for the move, Full IT de-com and re-com of all staff PCs.
- Full office furniture moves and installation.